WE REQUIRE DETAIL FOR 1 HR RATED SHAFTWALL TO THE UNDERSIDE OF A NON-RATED METAL ROOF DECK.

Posted by Ananya Baruaover 1 year ago
WE REQUIRE DETAIL FOR 1 HR RATED SHAFTWALL TO THE UNDERSIDE OF A NON-RATED METAL ROOF DECK.

WE REQUIRE DETAIL FOR 1 HR RATED SHAFTWALL TO THE UNDERSIDE OF A NON-RATED METAL ROOF DECK.

1 HR SHAFT WALL,NON-RATED METAL ROOF DECK

1 Reply
Posted by GHINA KABBARAover 1 year ago
Hilti Verified

Hi Ananya,
There is no existing tested system for this application. To have the case evaluated for an Engineering Judgement, please submit your request through the Hilti Construction Platform on the link below and we will get back to you as soon as possible: https://hcp.hilti.com.

EJ